- APRIL 23, 2011
Reactor Team Let Pressure Soar
By PHRED DVORAK
TOKYO—The operator of Japan's stricken nuclear plant let pressure in one reactor climb far beyond the level the facility was designed to withstand, a decision that may have worsened the world's most serious nuclear accident in a quarter century.
Japanese nuclear-power companies are so leery of releasing radiation into the atmosphere that their rules call for waiting much longer and obtaining many more sign-offs than U.S. counterparts before venting the potentially dangerous steam that builds up as reactors overheat, a Wall Street Journal inquiry found.
Japan's venting policy got its first real-world test in the chaotic hours after March 11's earthquake and tsunami knocked out cooling systems at the Fukushima Daiichi nuclear-power complex. By the first hours of March 12, an emergency was brewing inside the plant's No. 1 reactor.
By around 2:30 a.m., the pressure inside the vessel that forms a protective bulb around the reactor's core reached twice the level it was designed to withstand. Amid delays and technical difficulties, it was another 12 hours before workers finished releasing radioactive steam from this containment vessel, via reinforced pipes, to the air beyond the reactor building.